Preview build. Not indexed.

Bathroom plumbing

A white bath with brass-finish waste, overflow and shower hose

Planning the pipework side of a bathroom: supplies, wastes, first and second fix, the information we need and the order in which each connection gets tested.

Bathroom plumbing as a service is about the room as a whole: where supplies and wastes run, which items move and how the work fits around other trades. If you only need one item changed, pick it from the bathroom job pages instead.

What the job involves

First fix places the hidden pipework, waste runs, valve bodies and supports before walls and floors are closed. Second fix hangs and connects the visible sanitaryware. Between them come boarding, waterproofing and tiling, which may be done by others. Moving a toilet or shower depends on the fall available for its waste, so that is looked at before a layout is treated as settled.

Decisions to make early

  1. Which fittings stay where they are and which move.
  2. Whether walls or floors will be opened.
  3. Concealed or exposed valves and cisterns, and how each concealed part will be reached later.
  4. Whether the home keeps its only toilet and washing facility working between stages.
  5. Who orders each item, and by what stage it must be on site.

What we need from you

A sketch with wall lengths, door swing and window; photos of the room from the doorway and of any visible pipes; the floor construction; where the soil stack runs outside; product sheets for chosen fittings; and any lease or freeholder conditions. In a flat, ask early how the shared water supply is isolated.

Safe first steps

Do not strip out before you know how each pipe will be capped and the water kept off. Find and test the stop valve. Have electrical points near the room checked by an electrician before water and power work overlap. In an older building, treat unknown boards, textured coatings and pipe lagging with caution, because they may contain asbestos and need testing before disturbance.

How it is checked

Concealed joints are put under water and inspected before they are covered. Ask for this to happen while you or the next trade can see it. Wastes are run for long enough to show leaks and poor falls. After second fix, every tap, flush and shower is used, access panels are confirmed to open and supplies are checked for hot and cold on the correct sides.

Planning points for a refit

Layout decisions usually start with the soil pipe position, clearances around each fitting, a compatibility checklist before buying, first fix preparation and a like-for-like suite swap. New rooms bring their own limits, whether an en-suite, a loft bathroom, a room below ground, a shower in a bedroom or easier-access fittings.

Basins raise questions about heights, pedestals, semi-pedestals, wall hung fixings, countertop bowls, undermounted bowls, corner models, vanity units, twin basins, removal, moving the position, slotted or unslotted wastes, click-clack plugs and bottle traps.

Adding a new toilet or altering drainage can bring building regulations into play. The downstairs toilet page shows the kind of questions involved. Email your plan and say which trades you already have; the contact form takes the written description first.

Keeping a record

Photograph the pipe runs before boards and tiles cover them, with a tape measure in the picture. Note where each valve and trap can be reached, and keep the instructions for concealed parts. Anyone repairing the room later will need to know which cartridge or cistern fittings sit behind the wall.

How it works

From enquiry to agreement

Send my job list
  1. 01

    Describe it

    What is wrong or what you want changed, where it is and when it started.

  2. 02

    Add your details

    Postcode, how to reach you and the days that suit.

  3. 03

    Email photos

    A close view, a wider view and any model label, with your reference.

  4. 04

    Agree it in writing

    The scope, who supplies parts and how the price is worked out.

Water escaping now

Do these three things first

Safety comes before the enquiry. Send the form afterwards for the repair and any making good.

  1. 01

    Turn it off

    Close the internal stop valve if it is safe to reach. It is often under the kitchen sink or where the supply enters.

  2. 02

    Stay clear of electrics

    Do not touch wet sockets, fittings or appliances. Switch off at the consumer unit only if the way to it is dry.

  3. 03

    Get someone to attend

    Phone someone who can come now. A web form is not the place for water that is still running.

One list, however many jobs

Add what needs fitting or replacing, tell us the postcode, then email photos.

Send my job list