Freestanding bath plumbing planned properly: waste position, depth under the floor, tap pipe routes, water company notice for large baths and leak testing.
A freestanding bath shows all sides, so its waste and tap pipes usually come up through the floor in exact positions. The plumbing is settled by three drawings, one each for the bath, the waste and the tap, plus knowledge of what is under your floor.
Check capacity and weight
Read the capacity to the overflow. Under the Water Fittings Regulations, installing a bath that holds more than 230 litres, measured to the centre line of the overflow, requires notice to the water company and its consent before work begins. Heavy materials such as stone or cast iron add a lot before any water goes in, so have a builder or surveyor consider the floor.
Mark the position
Place a card template or the empty bath in the room. Check access for cleaning all round and the route to carry it in. A Heritage fitting guide asks for at least a 50 mm gap between a freestanding bath and the wall to allow movement as people get in and out. Your chosen bath may ask for more.
Waste under the floor
Approved Document H gives a bath trap of 40 mm with a 50 mm seal, and shows an unventilated branch of up to 3 m in 40 mm pipe or 4 m in 50 mm, falling 18 to 90 mm per metre.
Investigate:
| Floor | Key questions |
|---|---|
| Timber | Joist direction and depth, trap space, ceiling below |
| Solid | Can a channel be formed without damaging damp protection or services |
| Over another flat | Consent, fire and sound construction, access |
Exposed waste designs lead to a visible trap or pipe, but the branch still needs fall. Concealed ones need a trap you can reach, often through an access hatch or a removable section. Do not build a joint into screed. Some baths enclose the waste and overflow inside an outer skin. One Heritage guide connects these while the bath is raised on blocks, and allows a 70 mm access hole in the skin where the waste can only be reached above floor level. Do this only if your bath's instructions allow it.
Tap options
- Floor standing filler: two supplies come up to a fixed base. It needs a rigid anchor in the floor.
- Deck mounted on the bath: only where the bath has a ledge and holes designed for it, with supplies reached underneath.
- Wall mounted: needs first fix pipes in a wall near enough for the spout to reach into the bath.
Match pressure to the fitting and keep the spout above the rim as its sheet shows. Provide isolating valves you can reach. A handset on a hose can fall into bath water, so fit whatever backflow device the maker supplies or specifies. See floor standing tap installation.
Hot water supply
A large bath may use more hot water than your cylinder or system supplies comfortably. Compare the fill volume with what you have. Approved Document G limits hot water delivered to a bath in new dwellings and certain conversions to 48°C; a blending valve is the usual means. Ask building control whether your work is caught.
Order of work
- Confirm drawings and floor construction.
- Run and clip first fix pipes, capped and tested.
- Lay the floor with accurate holes and access.
- Anchor the tap base.
- Position and level the bath.
- Connect the waste and check every joint under a full discharge.
Fill to the overflow, empty it quickly and look below before closing the access.
Enquiring
Email the bath, tap and waste links, a floor sketch and photographs after a short note on the contact form. Flooring, structural work and decoration are separate.
Questions people ask
Where should a freestanding bath waste be?
Where the bath's drawing puts its outlet, with room under the floor for the trap and a falling pipe. Decide that before floor finishes.
Does a big bath need permission from the water company?
A bath over 230 litres to the overflow centre line must be notified before installation.