Moving a shower means new waste fall, supply pipes, wall sealing and electrical checks. See what limits the new position and which details to send us first.
A shower can move if the new position has a workable drain route, supplies with enough flow, walls that can be waterproofed and electrics that stay within the rules. The plumbing covers waste and water; finishes and wiring are separate work.
Drainage
Approved Document H gives a shower trap of 40 mm with a 50 mm seal, and for an unventilated bath branch shows up to 3 m in 40 mm pipe or 4 m in 50 mm, falling 18 to 90 mm per metre; confirm what suits a shower run. The new trap needs depth below the floor or a raised tray, and the pipe needs a route that does not cut joists improperly.
Where gravity will not work, a pumped unit may be an option. Approved Document G allows a washing appliance on a macerator and pump with small bore drainage only where there is also access to washing facilities that drain by gravity, and where the unit meets the lifting plant standard it names.
Water
Supplies must be extended without burying joints. Longer pipes lose some pressure and take longer to run hot. Check what the valve needs against what your system gives. A pump or a different valve changes the design, and some pumps must be notified to the water company.
Electrical position
In England, the special location around a shower reaches 2.25 m up, or to a higher fixed head, and 0.6 m out from a tray, or 1.2 m from a fixed head where there is no tray. New circuits, and additions or alterations within that zone, are notifiable. An electric shower also has its own cable to be moved or replaced by a registered electrician.
Walls and floor
| Check | Why |
|---|---|
| Wall construction | Fixings, valve depth and waterproof backing |
| External wall | Limits rear access and hidden pipes |
| Window or sloped ceiling | Splash zone and head height |
| Floor stiffness | Movement breaks seals |
| Old position | Capping, patching and floor repair |
Tanking and tiling are what keep water out of the structure, so decide who does them before the old shower is removed.
What to send
- photographs of the present shower, valve and tray waste access;
- the proposed position with a dimensioned sketch;
- location of the soil stack, cylinder or boiler cupboard, without opening anything;
- floor type and rooms below;
- product links already chosen;
- landlord or freeholder approval where needed.
Scope to confirm
Ask which pipes will be renewed, how the old ends are removed, what testing happens before the walls close, who restores finishes and what happens if hidden pipework differs from expectations. Any change to a gas boiler is quoted separately and done only by a Gas Safe registered engineer.
Start with the contact form, giving your postcode and the distance of the move. Then email the pictures with the reference. Prices are not published; a figure follows only once the details are understood. For a change in the same spot, shower tray fitting is the better page.
Questions people ask
What usually stops a shower being moved?
The waste. If it cannot fall to the drain from the new position, the tray has to be raised, pumped or placed elsewhere.